Top of the Hill Community Centre

Scope:
This Project involves construction of a split level facility incorporating facilities for Hillcrest Trust, Jack & Jill Pre-school, youth club and a 220m2 sports hall. Car parking, landscaping and an access road will also be constructed. The proposed project is located off the Trench Road adjacent to a new social housing development currently under construction.
Timeframe:
Construction has commenced on 14th January 2019, the construction period is 14 months.
Value:
£2.25 Million
Funding Partner:
Department For Communities